When healthcare projects are passed from designers over to the General Contractor for the start of construction, the transition should be seamless for all parties at the table, including the owner. However, as many healthcare facility managers know all too well, this becomes a new fast-paced chapter, sometimes filled with “growing pains” for their maintenance team, vendors, and staff. As an advocate for the owner, architects and engineers at Design Collaborative have plenty of experience with this shift of focus. Once the groundbreaking is complete and shovels start flying, there are a few key items to launch the first discussions in the jobsite trailer on day one.
|
The KickoffIt may seem like a simple tip, but the General Contractor should be encouraged to schedule a construction kick-off meeting, with a robust agenda. It’s beneficial to invite as many attendees to the table as they are available, including any end user groups impacted by the immediate start of construction. Additional Tips:
|
|
|
Not Just a PhaseIf an overall phasing plan has been created by the General Contractor, we advise it to be discussed early and at the top of the kick-off meeting agenda. Hospitals and outpatient facilities have numerous parallel flows of traffic, including patients, staff, and support vendors entering and exiting throughout the day. Ideally, the Contractor comes with a phasing diagram draft to discuss with the owner’s leadership team. It’s critical to flag any non-negotiable shutdowns or any intolerable overlap prior to construction because this will affect sequencing of construction, schedule, and perhaps cost. Additional Tips:
|
ICRA wallsConstruction managers are ultimately responsible for the purchasing/installation of ICRA (Infection Control Risk Assessment) walls and other ICRA components¹. Installing these temporary walls takes careful coordination between the GC and the owner, in order not to obstruct general staff corridor traffic or reduce emergency paths. Additional Tips:
|
|
|
Sensitive Equipment in-useDue to the sensitivity of patient diagnostic equipment, imaging projects come with their own precise levels of coordination. Prior to any construction kick-off meeting, temporary imaging mobile units should be discussed between the designer and owner. Prior to any site mobilization, if it has been flagged by the designer or owner, the Contractor should come to a pre-construction meeting with a subcontractor specialized in active construction site surveying techniques that can monitor vibrations in an existing building. MRI rooms are usually located on an exterior wall, so if there is a construction path or underground work being done adjacent, the Contractor should work with the imaging department for a plan to minimize disturbance. |
Rooftop RumbleWhile there is never a good time for a hospital roof system to leak, the worst time is during construction, when there are other factors in flux affecting the interior condition. The contractor should be extremely aware of any potential vibrations caused by their construction process that may dislodge fireproofing material from the underside of decks or beams, compromising the fire protection and handing an inspector an item to flag. Our design team takes great care to never position possible leak sources – roof drains & RTU equipment – above critical health services (ICU’s, surgical suites, patient rooms, MRI suites, Cath labs, radiology suites, pharmacies, etc.) Attention should be paid not only in design, but also during construction above these areas: vibrations that create noise to staff in these areas are intolerable and should be avoided, or flagged during phasing. |
|
|
Hold the DrywallWe have found it incredibly valuable to host what’s called “rough-in walkthrough’s” with the owners, the GC, and the electrical subcontractor, prior to drywall being installed. This method is valuable in any space type, including patient overnight room, ICU’s, Operating Rooms, Lab Draws, any staff conference rooms with a large amount of AV, nurse stations, and any other general locations with casework. We encourage the Contractor to schedule the walkthrough prior to drywall being installed and when all final power, data, and med gases are located on the walls in the room. The end users are invited to walk around the spaces and visualize the flow of the room during their daily routines. Even months after the design process is complete, we find that when surgeons, techs, physicians, and other staff are able to physically walk through their soon-to-be space, they can best tangibly visualize where they might need an additional power outlet, or other tweaks to lighting controls, etc. Additional Tip:
|
[footnotes]
Megan has an unmatched focus when she is working on a project. She listens carefully to each clients’ needs and digs deep into every detail to ensure that all projects are designed to best suit them. Megan’s Evidence-Based Design Accreditation & Certification helps her develop design solutions that are rooted in research to help achieve…